Roadwork and Utility Updates: June 24
 
Posted on Thursday June 24, 2021
 
June 24, 2021: REMINDER: Limekiln Pike Bridge Full Closure 6/25-6/28 PECO Milling and Paving Locations Beginning June 30
 

Roadwork Sign

June 24, 2021
PECO Milling and Paving Locations Beginning June 30
As part of the PECO Energy gas main replacement project, Kehoe Construction, Inc. will be performing final roadway milling/paving at the following locations beginning on June 30th and continuing into the following week of July 5th (no work will be performed on the 4th of July holiday celebrated on Monday, July 5th).

  • Oak Lane Rd from New Second St to Cheltenham Ave
  • Asbury Ave from Cheltenham Ave to Coventry Ave
  • Valley Rd from Oak Lane Rd to Coventry Ave
  • Chestnut Ave from Cheltenham Ave to Valley Rd
  • Crest Ave from Valley Rd to Chestnut Ave
  • Oak Ave from Cheltenham Ave to Valley Rd
  • Richards Rd from Asbury to the dead end
  • 4th Ave from Asbury Ave to High Ave
  • High Ave from 4th Ave to New Second St
  • Sunnybrook Ave from 4th Ave to Oak Lane Rd

Work will take place weekdays between 9:00 AM and 3:00 PM on Oak Lane Rd (a state road), and between 7:30 AM and 4:00 PM on the other local streets.  The road will typically be kept open to one lane of traffic in both directions with traffic control flaggers, but a temporary closure may be required at certain times.  Trash/recycling collection, mail/package delivery, and residents' access to their homes will be kept available by the contractor.  Questions regarding this project can be directed to the Kehoe project manager, Steve Witt, at 484-576-7154.

Limekiln Pike Bridge over SEPTA

This state bridge is located near the intersection of Limekiln Pike and Mt. Carmel Avenue.  PennDOT is currently working on replacing the bridge superstructure, and two-way traffic on the bridge is typically being maintained during this project. However, in order to facilitate the removal of certain existing bridge deck beams, PennDOT is allowing the contractor to institute a full bridge closure with detour commencing on Friday, June 25th at 7PM and continuing through Monday, June 28th until 5AM.  After that time two-way traffic flow will be reestablished on the bridge for the continuing reconstruction project.

View Traffic Detour Plan

At this point in time, one additional full bridge weekend closure is anticipated during July.  A specific notification will be issued in advance of that closure.  The project is currently scheduled to be completed before Thanksgiving Day 2021.


June 17, 2021

Chelten Hills Drive Closure Friday, June 18
Tomorrow, June 18, Public Works will be closing Chelten Hills Drive between Heacock Lane and Church Road to remove a large tree from the creek and perform some road shoulder maintenance. The road will be closed for approximately 4.5 hours to all traffic including emergency vehicles between 9:15am and 1:45pm. Detour signage will be set up utilizing Greenwood Avenue and Church Road. A "Road Closed Ahead" sign will be placed on Glenside Avenue at Greenwood Avenue, and the road will be barricaded off at Heacock Lane and Church Road. 

June 15, 2021
PECO Contractor Performing Trench Restoration 6/16-21
As part of the PECO Energy gas main replacement project, Kehoe Construction, Inc. will be performing trench restoration at the following locations beginning on June 16th and continuing into the following week of June 21st. 

  • Oak Lane Rd from New Second St to Cheltenham Ave
  • Asbury Ave from Cheltenham Ave to Coventry Ave
  • Valley Rd from Oak Lane Rd to Coventry Ave
  • Chestnut Ave from Cheltenham Ave to Valley Rd
  • Crest Ave from Valley Rd to Chestnut Ave
  • Oak Ave from Cheltenham Ave to Valley Rd
  • Richards Rd from Asbury to dead end
  • 4th Ave from Asbury Ave to High Ave
  • High Ave from 4th Ave to New Second St
  • Sunnybrook Ave from 4th Ave to Oak Lane Rd

Final roadway milling/paving will be performed at a later date.  Work will take place weekdays between 9:00 AM and 3:00 PM on Oak Lane Rd (a state road), and between 7:30 AM and 4:00 PM on the other local streets.  The road will typically be kept open to one lane of traffic in both directions with traffic control flaggers, but a temporary closure may be required at certain times.  Trash/recycling collection, mail/package delivery, and resident’s access to their homes, will be kept available by the contractor.  Questions regarding this project can be directed to the Kehoe project manager, Steve Witt, at 484-576-7154.


June 8, 2021

Aqua Roadway Restoration Work at the Following Locations
On June 8, 2021 A. Giuliani Co., an Aqua contractor, will begin performing final roadway restoration (milling and paving) at the following locations on the dates specified (weather permitting):

  • Arbor Road from Ashbourne Road to Pitt Road on June 8th and 9th
  • Boyer Road from Ashbourne Road to Rowland Avenue on June 8th and 9th
  • Pitt Road from Arbor Road to Croyden Road on June 8th and 9th
  • Boyer Road from Rowland Avenue to Gilbert Road on June 10th and 11th
  • Gilbert Road from Ashmead Road to Croyden Road on June 10th and 11th
  • Rowland Avenue from Ashmead Road to Croyden Road on June 10th and 11th
  • Croyden Road from Rowland Avenue to dead end on June 10th and 11th

Work will take place between 7:30AM and 5:30PM.  Access will be provided for emergency, mail, school bus and trash services.  Residents will have access to their properties but at times may need to enter from a different direction due to changing work zones.

Questions regarding this project can be directed to A. Giuliani Co.at 215-643-6166.

Ogontz Ave Traffic Signal Replacement Beginning June 15
Starting on June 15, 2021 and ending on June 18, 2021 crews will be replacing the traffic signal equipment along Ogontz Ave between Greenwood Avenue and Cheltenham Avenue.  All of the work will take place between the hours of 9:00am and 3:00pm.  During this time, the traffic lights will be turned off and flagging crews will be directing traffic at the intersections.  Please plan accordingly as there will be delays in the area.  All work is weather dependent.


June 4, 2021
Tookany Creek Parkway and Trail Emergency Tree Work Closure
There will be a closure of Tookany Creek Parkway between Beryl Road and Central Avenue starting Monday, June 7 for emergency removal of hazardous trees in the area of the playground next to Veterans Memorial Field.  This section of the walking trail will be closed as well.  Signs and barricades will be present.  Work will be conducted between the hours of 9:00 am - 4:00 pm, and will be a 3-day project beginning Monday, weather-permitting.

June 2, 2021

PECO Electric Cable Replacement on Paxson Avenue
On June 1, 2021 Miller Bros., a PECO contractor, began an underground electric cable replacement project on Paxson Avenue, between South Avenue and North Avenue.  Work will take place weekdays between 7:30AM and 4:00PM and is anticipated to take approximately 4 weeks to complete (weather permitting).   Access will be provided for emergency, mail, school bus, and trash services.  Residents will have access to their properties but at times may need to enter from a different direction due to changing work zones.
Questions regarding this project can be directed to the Miller Bros Project Manager, Tom Stewart, at (610) 283-9275.

May 25, 2021

PennDOT Work Scheduled for 5/27 on Greenwood Ave; Traffic Not Impacted
The PennDOT drilling contractor will be working along the east side of Greenwood Avenue this Thursday, 5/27, north of Church Road.  Work will be off of the roadway and will not impact traffic.  Please contact the PennDOT Project Manager, Curt Venditti (610.205.6853), with any questions.

May 24, 2021
Limekiln Pike Bridge over SEPTA Update
PennDOT is currently working on replacing the bridge superstructure near Limekiln Pike and Mt. Carmel Avenue.  Two-way traffic on the bridge is being maintained during this project.  A 10-week look-ahead schedule starting Monday, May 24, 2021 may be viewed here.  The next full bridge closure is scheduled for the weekend of June 25-28, 2021.  A specific notification will be posted in advance of the closure.  The project completion date is currently scheduled for December 21, 2021.

PECO Natural Gas Equipment Replacement Work Week of 5/24
Henkels & McCoy, a PECO contractor, will continue work in the following areas this week:

  • Old York Rd and Stratford Ave
  • Ashbourne from Spring Ave to Old York Rd
  • Spring Ave from Stratford Ave to Mountain Ave
  • Lodges Ln from Spring Ave to West Ave
  • West Ave from Ashbourne Rd to Prospect Ave
  • Chapel Rd from West Ave to Spring Ave
  • Ansley Ave from Old York Rd to Sharpless Rd
  • Sharpless Rd from Ansley Ave to Mountain Ave
  • Mountain Ave from Valley Rd to Stratford Ave
  • Webb Rd from Whitewood Rd to Old York Rd

Work will be completed from 9:00am-3:00pm.  The project may occur on roadways, sidewalks, or potential on private property, with customers notified ahead of time. For more information, please contact David Spatichia: 215-341-8903.

May 21, 2021

Aqua Milling and Paving beginning 5/24 at the Following Locations
A. Giuliani Co., an Aqua contractor, will continue performing final roadway restoration (milling and paving) at the following locations on the dates specified (weather permitting):

  • On May 24: Laurel Avenue, from Yew Road to just beyond the bend part Myrtle Ave, #433 Laurel Avenue
  • On May 26: Central Ave from Tookany Creek Pkwy to Highland Rd, Highland Rd to Rowland Ave

Work will take place between 7:30AM and 5:30PM.  Access will be provided for emergency, mail, school bus and trash services.  Residents will have access to their properties but at times may need to enter from a different direction due to changing work zones.

Questions regarding this project can be directed to Vince Giuliani at 215-643-6166.

May 12, 2021
Phase 2 of Texas Eastern Pipeline Project starting June 3
Texas Eastern Transmission, LP (TETLP)  is an interstate natural gas transmission company.  In 2020 they completed Phase 1 of a pipeline relocation project along Tookany Creek Parkway, in the vicinity of the Jenkintown Road intersection, which involved the construction of a new bypass pipeline.  On June 3, 2021 Texas Eastern will commence Phase 2 of this project, which involves the connection of the new bypass pipeline to the existing pipeline within Tookany Creek Parkway, and removal of the abandoned section  of pipeline.  Work will take place weekdays between 7:30 AM and 5:30 PM.  During this period, traffic will be maintained through the work area with appropriate signage and flaggers.  There will be no full-road closures or detours.  Construction activities are anticipated to be completed by June 30, 2021 (weather permitting).

Questions regarding this project can be directed to Robert Winter, TETLP Right of Way Supervisor, at (518) 542-3177.

PECO Gas Pipeline Replacement beginning 5/24 in Following Locations
On May 24, 2021, PECO will begin replacing underground natural gas pipeline at the following locations:

  • Ashbourne Rd from Old York Rd to Spring Ave
  • West Ave from Ashbourne Rd to Prospect Ave
  • Chapel Rd from Lodges Ln to Ashbourne Rd
  • Spring Ave from Mountain Ave to Ashbourne Rd

This project will be performed by Henkels & McCoy, a PECO contractor, weekdays between 9:00 AM and 3:00 PM on Ashbourne Rd (a state road), and between 7:30 AM and 3:00 PM on the other local streets.  During this period, traffic will be maintained through the work area with appropriate signage and flaggers, although due to the location of the new pipe, a temporary road closure on local streets may be required at certain times.  Trash/recycling collection, mail/package delivery, school bus service, and resident’s access to their homes, will be kept available by the contractor.  The natural gas main and service line installation portion of this project is anticipated to be completed in 16 weeks.

Questions regarding this project can be directed to David Spatichia of Henkels & McCoy at 215-341-8903.

April 28, 2021
PECO Natural Gas Equipment Replacement Starting May 3
On May 3, 2021, PECO will begin replacing existing natural gas equipment in the area of Laurel Ave, between Township Line Rd and Yew Rd, and Yew Rd, between Laurel Ave and Krewson Ln (westerly intersection).  This project includes the installation of new underground pipe which is more durable, enhances safety and improves service reliability.  The work will be performed by General Asphalt Paving Co (GAP), a PECO contractor, weekdays between 7:30 a.m. and 4:30 p.m., and will occur in roadways as well as on sidewalks and potentially on private property.  PECO anticipates the natural gas main and service line installation portion of this project will be completed in 8 weeks.  Questions regarding scheduling or the project can be directed to Joe Meehan of GAP at 267-688-2170.

April 27, 2021
Coventry Rd Closure 5/1 for Utility Pole Replacement
On Saturday, May 1, Coventry Road will be closed for utility pole replacement between Stratford Ave and Windsor Ave. There will be flagmen on both sides of the construction area directing traffic around the road closure up onto Woodland Road. The closure is expected to be from 8am-4pm. Motorists should use caution if traveling in that area on Saturday, and avoid the area if possible during the posted construction times.

April 23, 2021
PECO Electrical Equipment Replacement on Mill Rd starting 4/26
PECO contractors will be replacing electrical poles along Mill Rd. from Windsor Ave to Valley Rd starting Monday, April 26. The work will occur between 7:00am-5:00pm and is expected to take 3 days, weather-permitting.  The crews will try to maintain a lane for traffic, but intermittent full closures will be necessary at times.  Residents are encouraged to use Woodlawn Avenue as a detour in the area. If you have any questions regarding the details of this project and how it may impact you, please contact Mike Herman at [email protected]

PECO Natural Gas Equipment Replacement starting 5/10
Henkels & McCoy, a PECO contractor, will begin work on May 10, 2021 in the area of Old York Road from Stratford Avenue to Ashbourne Road from 9:00am-3:00pm.  The project may occur on roadways, sidewalks, or potential on private property, with customers notified ahead of time. The project is expected to take 16 weeks. For more information, please contact David Spatichia: 215-341-8903.

April 16, 2021
Aqua Emergency Sewer Repairs April 19-20

On April 19 and 20, Aqua Wastewater will be performing emergency sanitary sewer repairs on Woodlawn Ave, between Windsor Ave and Towanda Ave.  It may be necessary to temporally close the road, but Aqua will maintain resident’s access to their properties.  For further information contact Hank Wacker, Aqua Field Supervisor, at 267-688-1833.


Limekiln Pike Bridge over SEPTA

This state bridge is located near the intersection of Limekiln Pike and Mt. Carmel Avenue.  PennDOT is currently working on replacing the bridge superstructure, and two-way traffic on the bridge is typically being maintained during this project.  However, due to unanticipated changes in the design and installation of PECO gas and Aqua water facilities, and the need to meet a set timetable for SEPTA train service interruptions and PECO electric service disruption, PennDOT is allowing the contractor to institute a full bridge closure with detour commencing on Saturday, April 24th at 7AM and continuing through Monday, May 17th until 5AM.  After that time two-way traffic flow will be reestablished on the bridge for the continuing reconstruction project.

View Traffic Detour Plan

An additional full bridge weekend closure is anticipated between June 25th and 28th for bridge beam erection.  A specific notification will be issued in advance of that closure.  The project is currently scheduled to be completed before Thanksgiving Day 2021.


April 9, 2021
PennDOT Announced Church Rd Lane Closure for April 19-20
Route 73 (Church Road) motorists will encounter a weekday lane closure with flagging between Rices Mill Road and Greenwood Avenue in Cheltenham Township, Montgomery County, on Monday, April 19, and Tuesday, April 20, from 8:00 AM to 3:00 PM


April 5, 2021

PECO Natural Gas Equipment Replacement beginning April 19
On April 19, 2021, PECO will begin replacing existing natural gas equipment in the area of Old York Road (SR 0611) from Stratford Avenue to Ashbourne Road.  This project includes the installation of new underground pipe which is more durable, enhances safety and improves service reliability.  The work will be performed by Henkels & McCoy, a PECO contractor, weekdays between 9:00 a.m. and 3:00 p.m., and will occur in roadways as well as on sidewalks and potentially on private property.  PECO anticipates the natural gas main and service line installation portion of this project will be completed in 16 weeks.  Questions regarding scheduling or the project can be directed to David Spatichia of Henkels & McCoy at 215-341-8903.


April 1, 2021

Henkles & McCoy Milling & Paving Work in Curtis Arboretum 4/6-7
Contractor Henkles & McCoy will be doing Milling and Paving work Tuesday 4/6 and Wednesday 4/7, weather permitting, inside Curtis Arboretum between the Dog Park and the Upper Pond Area.

Dog Park users should use the Washington Lane entrance only to access the Dog Park.  All other users for the Arboretum should use the Church Road entrance only.  The lower section between the ponds will be closed until the Milling and Paving project has been completed.


March 31, 2021

PECO Service Connection Upgrades Starting 4/6
PECO
recently completed installation of natural gas mains and service lines at the locations shown below, and will now begin upgrading service connections to homes in that area. 

  • Mountain Ave from Valley Rd to Stratford Ave
  • Sharpless Rd from Ansley Ave to Mountain Ave
  • Ansley Ave from Old York Rd to Sharpless Rd

Work is scheduled to start on April 6, 2021 and will be performed by Henkels & McCoy, a PECO contractor.  This project is expected to last approximately eight weeks.  In order to safely connect homes to the new natural gas main, PECO will need to turn off natural gas service and then enter the property to relight appliances after the connection is completed.  At that time, they also will be relocating any indoor natural gas meters to the exterior of customer homes.  PECO crews and contractors will be following all COVID-19 safety protocols.  PECO will deliver notices to those properties affected so that homeowners may arrange a convenient time for this work to occur.  Any areas impacted on resident’s property will be restored to their original condition.  Questions regarding the project can be directed to David Spatichia of Henkels & McCoy at 215-341-8903.

Aqua Trench Restoration in Ward 7 locations begins April 5
On April 5, 2021 Aqua contractor, Caddick Utilities LLC, will begin the trench restoration work for water main installations at the following locations, in the order shown:

  • Boyer Rd from Ashbourne Rd to Gilbert Rd
  • Gilbert Rd from Boyer Rd to Croyden Rd
  • Croyden Rd from Gilbert Rd to Pitt Rd
  • Pitt Rd from Croyden Rd to Arbor Rd
  • Arbor Rd from Pitt Rd to Ashbourne Rd
  • Rowland Ave from Croyden Rd to Ashmead Rd
  • Gilbert Rd from Ashmead Rd to Boyer Rd

Work hours will be Monday through Friday, 7:30 AM to 4:00 PM.  The entire project is anticipated to take approximately four weeks to complete, weather permitting.  Final roadway milling/paving will be performed at a later date.  Access will be provided for emergency vehicles, mail delivery, school buses and trash service.  Residents will have access to their properties, but at times may need to enter from a different direction due to changing work zones.  For any questions regarding the project, contact the Caddick Office during normal business hours at 215-653-0260.

Limekiln Pike Bridge over SEPTA

This state bridge is located near the intersection of Limekiln Pike and Mt. Carmel Avenue.  PennDOT is currently working on replacing the bridge superstructure, and two-way traffic on the bridge is typically being maintained during this project.  However, in order to allow Aqua to install their new pipes and tie them back into their existing system, PennDOT is allowing the contractor to institute nightly full bridge closures beginning on Sunday, 4/4/21, and continuing through Saturday, 4/10/21, from 9:00 PM to 6:00 AM.  After that time two-way traffic flow will be reestablished on the bridge for the continuing reconstruction project.

View Traffic Detour Plan

Two additional full bridge weekend closures are anticipated over the coming year for bridge beam removal/erection.  These are currently scheduled for 5/14 to 5/17 and for 6/25 to 6/28.  Specific notifications will be issued in advance of each closure.  The project completion date is currently scheduled for 12/21/21.

March 30, 2021
PECO Natural Gas Pipeline Replacements 3/31 - Wards 3 and 5 locations
On March 31, 2021, PECO will begin replacing existing natural gas pipeline at the following locations:

  • Old York Rd from Ansley Ave to Stratford Ave (9:00 AM to 3:00 PM)
  • Stratford Ave from Old York Rd to Mountain Ave (7:30 AM to 3:30 PM)

This project will be performed by Henkels & McCoy, a PECO contractor.  Work will occur in roadways as well as on sidewalks and potentially on private property.  Local traffic will typically be maintained through the work area with appropriate signage and flaggers.  Trash/recycling collection, mail/package delivery, school bus service, and resident’s access to their homes, will normally be maintained by the contractor.  However, due to the location of the new pipe, a temporary road closure may be required at certain times.  In such instances, Henkels & McCoy staff will be available to provide access assistance if necessary.  PECO anticipates that the natural gas main and service line installation portion of this project will be completed in 16 weeks.  Questions regarding the project can be directed to David Spatichia of Henkels & McCoy at 215-341-8903.

March 29, 2021
Limekiln Pike Bridge over SEPTA Update
PennDOT is currently working on replacing the bridge superstructure near Limekiln Pike and Mt. Carmel Avenue.  Two-way traffic on the bridge is being maintained during this project.  A 9-week look-ahead schedule starting Monday, March 29, 2021 may be viewed here.  The next 7 weeks of the schedule are accelerated to meet the next full bridge closure, scheduled for the weekend of May 14-17, 2021.  A specific notification will be posted in advance of the closure.  The project completion date is currently scheduled for December 21, 2021.

March 27, 2021
PennDOT announces lane closures on Route 309 3/29-4/2

Periodic lane closures are scheduled next week on Route 309, in both directions, between the Route 152 Interchange and Greenwood Avenue on Monday, March 29, through Friday, April 2, from 9:00 AM to 3:00 PM, for line striping and delineator installations under a project to install safety enhancements to improve travel and reduce high-speed crashes, PennDOT announced.

Motorists are advised to allow extra time when traveling through the work areas because backups and delays may occur. All scheduled activities are weather dependent.

March 17, 2021
Limekiln Pike Bridge over SEPTA

This state bridge is located near the intersection of Limekiln Pike and Mt. Carmel Avenue.  PennDOT is currently working on replacing the bridge superstructure, and two-way traffic on the bridge is typically being maintained during this project.  However, in order to facilitate a bridge deck concrete pour operation, PennDOT is allowing the contractor to institute a full bridge closure with detour
commencing at 8:00 PM on Monday, 3/22/21 and ending at 4:00 AM on Tuesday, 3/23/21.  After that time, two-way traffic flow will be reestablished on the bridge for the continuing reconstruction project.

View Traffic Detour Plan

Two additional full bridge weekend closures are anticipated over the coming year for bridge beam removal/erection.  These are currently scheduled for 5/14 to 5/17 and for 6/25 to 6/28.  Specific notifications will be issued in advance of each closure.  The project completion date is currently scheduled for 12/21/21.


March 15, 2021

PECO Replacing Natural Gas Pipeline on Ashbourne Road between Old York and Spring starting 3/19
On March 19, 2021, PECO will begin replacing underground natural gas pipeline on Ashbourne Road (State Route 2025) between Old York Road and Spring Avenue.  This project will be performed by Henkels & McCoy, a PECO contractor, weekdays between 9:00 AM and 3:00 PM.  Work is expected to last approximately four weeks.  During this period, traffic will be maintained through the work area with appropriate signage and flaggers.  Trash/recycling collection, mail/package delivery, school bus service, and resident’s access to their homes, will be kept available by the contractor. 

Questions regarding this project can be directed to: Joseph Welte - Henkels & McCoy Project Manager - 215-377-1959


March 12, 2021
PECO pipeline replacements beginning 3/15
On March 15, 2021, PECO will begin replacing existing natural gas pipeline, with anticipated completion of natural gas main and service line installation within 12 weeks at these locations:

  • Webb Road, between Old York Road and Whitewood Road
    • Whitewood Road, between Webb Road and Spring Avenue

 PECO pipeline replacements beginning 3/17:
On March 17, 2021, PECO will begin replacing existing natural gas pipeline, with anticipated completion of natural gas main and service line installation anticipated in 16 weeks, at these locations:

  • Prospect Ave, from Mountain Ave to West Ave
  • Spring Ave, from Prospect Ave to Mountain Ave
  • Lodges Ln, from Spring Ave to West Ave
  • Chapel Rd, from West Ave to Lodges Ln

The above projects will be performed by Henkels & McCoy, a PECO contractor, weekdays between 7:30 AM and 3:30 PM.  Work will occur in roadways as well as on sidewalks and potentially on private property.  Local traffic will typically be maintained through the work area with appropriate signage and flaggers.  Trash/recycling collection, mail/package delivery, school bus service, and resident’s access to their homes, will normally be maintained by the contractor.  However, due to the location of the new pipe, a temporary road closure may be required at certain times.  In such instances, Henkels & McCoy staff will be available to provide access assistance if necessary.  Questions regarding the project can be directed to David Spatichia of Henkels & McCoy at 215-341-8903.

UPDATED: PECO Gas Main Replacement Trench Restoration Taking Place 3/16-3/19
Per the earlier (3/2, 3/9) posts regarding this part of the PECO Energy gas main replacement project, Kehoe Construction, Inc. has completed the concrete sawing operation on schedule and will now be performing the trench restoration at the following locations from Tuesday, March 16 through Friday, March 19 (weather permitting).

  • Keswick Ave from Waverly Rd to Paxson Ave (including stub-out locations on encompassed side streets: Wesley Ave, Parkside Ln, Brookdale Ave and Glenside Ave).
  • New St from Keswick Ave to Glenside Ave.

Final roadway milling/paving will be performed at a later date.  Work will take place between 7:30 AM and 4:00 PM.  The road will typically be kept open to one lane of traffic in both directions with traffic control flaggers, but a temporary closure may be required at certain times.  Residents will have access to their properties.  Kehoe staff members will be available to provide assistance.  INFO: Kehoe Foreman Steve Witt at 484-576-7154.

March 11, 2021

Aqua Contractor to Begin Trench Restoration Work March 15
On March 15, 2021 Aqua contractor, Caddick Utilities LLC, will begin the trench restoration work for water main installations at the following locations:

  • Central Avenue from Ashbourne Road to Highland Road
  • Highland Road from Central Avenue to Rowland Avenue
  • Laurel Avenue from Township line Road to past Myrtle Avenue
  • Beecher Avenue from Laurel Avenue to Elm Avenue
  • Franklin Avenue from Laurel Avenue to Grove Avenue

Work hours will be Monday through Friday, 7:30 AM to 4:00 PM.  The entire project is anticipated to take approximately three weeks to complete, weather permitting.  Final roadway milling/paving will be performed at a later date.  Access will be provided for emergency vehicles, mail delivery, school buses and trash service.  Residents will have access to their properties, but at times may need to enter from a different direction due to changing work zones.  For any questions regarding the project, contact the Caddick Office during normal business hours at 215-653-0260.


March 9, 2021

UPDATE to below March 2, 2021 Posting: Due to unexpected subsurface roadway conditions, Kehoe had to temporarily halt the trench restoration work that was underway.  A special concrete sawing operation is now scheduled from Wednesday, March 10 through Friday, March 12, after which the trench restoration operation will be resumed.  A subsequent posting will be issued when the dates for this work have been determined.
March 2, 2021
PECO Gas Main Replacement Trench Restoration Taking Place 3/4-3/9

As part of the PECO Energy gas main replacement project, Kehoe Construction, Inc. will be performing trench restoration at the following locations from Thursday, March 4th through Tuesday, March 9th (weather permitting).

  • Keswick Ave from Waverly Rd to Paxson Ave (including stub-out locations on encompassed side streets: Wesley Ave, Parkside Ln, Brookdale Ave and Glenside Ave).
  • New St from Keswick Ave to Glenside Ave.

Final roadway milling/paving will be performed at a later date.  Work will take place between 7:30 AM and 4:00 PM.  The road will typically be kept open to one lane of traffic in both directions with traffic control flaggers, but a temporary closure may be required at certain times.  Residents will have access to their properties.  Kehoe staff members will be available to provide assistance.  INFO: Kehoe Foreman Steve Witt at 484-576-7154.


March 5, 2021
PECO Gas Main Replacement Trench Restoration on New Second St. 3/4-3/9
As part of the PECO Energy gas main replacement project, Kehoe Construction, Inc. will be performing trench restoration on New Second Street, between Coventry Avenue and Cheltenham Avenue, from Tuesday, March 9th through Friday, March 12th (weather permitting).  Final roadway milling/paving will be performed at a later date.  Work will take place between 9:00 AM and 3:00 PM.  The road will be kept open to one lane of traffic in both directions with traffic control flaggers.  Residents will have access to their properties.  Kehoe staff members will be available to provide assistance.

INFO: Kehoe Foreman Steve Witt at 484-576-7154.

Gas
Odor/Leak on Foxcroft Road
PECO has identified a low-grade leak at this location.  Based on its classification, it does not need immediate attention.  PECO is planning to replace this section of main in the 2022 AIGMP program.  We are going to attempt to clear it in the near-term and monitor it.
The Township Manager and Fire Marshal have been out to the location.  For more information, or if you smell an odor, please dial 911.


March 2, 2021

PECO Gas Main Replacement Trench Restoration Taking Place 3/4-3/9

As part of the PECO Energy gas main replacement project, Kehoe Construction, Inc. will be performing trench restoration at the following locations from Thursday, March 4th through Tuesday, March 9th (weather permitting).

  • Keswick Ave from Waverly Rd to Paxson Ave (including stub-out locations on encompassed side streets: Wesley Ave, Parkside Ln, Brookdale Ave and Glenside Ave).
  • New St from Keswick Ave to Glenside Ave.

Final roadway milling/paving will be performed at a later date.  Work will take place between 7:30 AM and 4:00 PM.  The road will typically be kept open to one lane of traffic in both directions with traffic control flaggers, but a temporary closure may be required at certain times.  Residents will have access to their properties.  Kehoe staff members will be available to provide assistance.

INFO: Kehoe Foreman Steve Witt at 484-576-7154.


 
February 26, 2021
PECO Gas Main Replacement Trench Restoration Wards 5 & 7, 3/1-3/3
As part of the PECO Energy gas main replacement project, Kehoe Construction, Inc. will be performing trench restoration at the following locations on Monday, March 1st through Wednesday, March 3rd (weather permitting).

  • Monday 3/1/21
    Parkview Rd from Front St to Rowland Ave
  • Tuesday 3/2/21
    Rowland Ave from Parkview Rd to Johns Rd
    Ivinetta Rd from Parkview Rd to Edgemoor Rd
    Johns Rd from Front St to Brookfield Rd (start)
  • Wednesday 3/3/21
    Johns Rd from Front St to Brookfield Rd (finish)
    Garden Rd from Edgemoor Rd to Johns Rd

Final roadway milling/paving will be performed at a later date.  Work will take place between 7:30 AM and 4:00 PM.  The road will typically be kept open to one lane of traffic in both directions with traffic control flaggers, but a temporary closure may be required at certain times.  Residents will have access to their properties.  Kehoe staff members will be available to provide assistance.

INFO: Kehoe Foreman Steve Witt at 484-576-7154.


February 23, 2021

PECO Energy Gas Main Replacement Project Update

As part of the PECO Energy gas main replacement project, Henkels & McCoy, Inc. will be performing the following work at the locations shown below over the next two weeks (weather permitting). These are the same locations given in a prior update on 2/16/21, but work was unable to be completed due to snow events.

  • Complete remaining service connections on the Bickley Rd/Forsythe Ave/Royal Ave/Toxony Ave project area.
  • Continue main installation work on Mountain Ave (Valley Rd to Stratford Ave), Sharpless Rd (Ansley Ave to Mountain Ave) and Ansley Ave (Old York Rd to Sharpless Rd).
  • Begin main installation work on Mountain Ave (Stratford Ave to Spring Ave), Melrose Ave (Mountain Ave to Old York Rd) and Spring Ave (Stratford Ave to Prospect Ave).

INFORMATION: Christopher Long, Henkels & McCoy Field Engineer, (215) 907 0847


January 19, 2021
PECO Energy Gas Main Replacement Work Jan. 21 - Feb. 2

As part of the PECO Energy gas main replacement project, Kehoe Construction, Inc. will be performing trench restoration at the following locations on Thursday, January 21st through Tuesday, February 2nd (weather permitting).

  • Thursday, January 21st
    Brookfield Road (Parkview Road to Andrea Road)
    Andrea Road (Brookfield Road to Waters Road)
  • Friday, January 22nd
    Waters Road (Boncouer Road to Hilldale Road)
    Hilldale Road (Waters Road to Front Street)
  • Monday, January 25th
    Front Street (Hilldale Road to Ashbourne Road)
  • Tuesday, January 26th
    Front Street (Parkview Road to Lanfair Road)
  • Wednesday, January 27th
    Parkview Road (Ivinetta Road to Rowland Avenue)
  • Thursday, January 28th
    Rowland Avenue (Parkview Road to Johns Road)
  • Friday, January 29th
    Ivinetta Road (Parkview Road to Johns Road)
    Garden Road (Edgemoor Road to Johns Road)
    Lawnside Road (Garden Road to Rowland Avenue)
  • Monday, February 1st
    Johns Road (Rowland Avenue to Front Street)
  • Tuesday, February 2nd
    Lanfair Road (Front Street to Ivinetta Road)

Final roadway milling/paving will be performed at a later date.  Work will take place between 8:00 AM and 4:00 PM.  The road will typically be kept open to one lane of traffic in both directions with traffic control flaggers, but a temporary closure may be required at certain times.  Residents will have access to their properties.  Kehoe staff members will be available to provide assistance.

INFO: Kehoe Construction at 610-279-0126.

December 4, 2020
PECO Contractor Trench Work on New Second Street Project Estimated Completion December 22

PECO expects to complete main work for the gas facilities installation project on New Second Street between Oak Lane Road and Coventry Avenue on December 22nd (barring any significant weather events or other emergencies). The main installation is complete and crews are currently working on services.  There are 30 services remaining to be done, 18 of which are scheduled already.  Final milling and paving will be scheduled at a later date after settlement of the trenches for final restoration.

November 6, 2020

Aqua Sewer Main Replacement Work beginning November 16

On November 16, 2020 Aqua Pennsylvania Wastewater will begin the replacement of 700 feet of 8-inch terra cotta sanitary sewer main with 8 inch PVC pipe on Hilldale Road between Waters Road and Front Street.  Construction will generally take place weekdays between 7:30 AM and 6:00 PM.  Access will be provided for emergency vehicles, mail delivery, school buses, and trash service.  Residents will have access to their properties, but at times may need to enter from a different direction due to changing work zones.

For any questions regarding the project, contact: Hank Wacker, Aqua Superintendent of Wastewater Construction, 267-688-1833.

October 29, 2020
Enbridge (Texas Eastern) Natural Gas Pipeline Work on Tookany Creek Parkway beginning November 3
Beginning on November 3, 2020 Enbridge (Texas Eastern) will be installing a new gas pipeline in the field to the south of Tookany Creek Parkway, between Jenkintown Road and Beryl Road.  This work is expected to take two to four weeks to complete.  The project will have minimal impact to the roadway; and walking trails will generally remain useable.  Work hours will be 7:30 AM to 5:30 PM, Monday through Saturday.  In the spring of 2021 this new pipeline in the field will be used to replace a parallel portion of an existing pipeline in the roadway that will have to be removed in advance of Tookany Creek Parkway bridge work scheduled for 2022.  Additional information about this future work will be provided closer to the actual commencement date.

October 28, 2020
PECO Soil Boring Work on Asbury Avenue beginning October 30
On October 30, 2020 and November 2, 2020 Boring Brothers Inc., a PECO contractor, will take soil borings on the edge of Asbury Avenue, between Coventry Avenue & Richards Road.  This work will take place between 8:00AM and 4:00PM.  Activity will be limited to the parking lane area, so impact to through traffic should be minimal.


October 23, 2020

Aqua Roadway Restoration Work beginning October 28

On October 28, 2020 A. Giuliani Co., an Aqua contractor, will begin performing final roadway restoration (milling and paving) at the following locations on the dates specified (weather permitting):

  • Glenview Avenue, between Park Lane and Hewett Road, from Wednesday October 28th until Friday October 30th
  • Waverly Road, between Hewett Road and Rices Mill Road, from Wednesday October 28th until Friday October 30th
  • Hewett Road, between Glenview Avenue and Rices Mill Road, from Monday November 2nd until Wednesday November 4th

Work will take place between 7:30AM and 5:30PM.  Access will be provided for emergency, mail, school bus and trash services.  Residents will have access to their properties but at times may need to enter from a different direction due to changing work zones.

If any questions regarding the project, please contact: Vince Giuliani at 215-643-6166

October 22, 2020
PECO Natural Gas Jack and Bore Work on Valley Road beginning November 4
On or about November 4, 2020 Henkels & McCoy, a PECO contractor, will begin a jack and bore operation on Valley Road, between Coventry Avenue and Chestnut Avenue.  This effort involves the excavation of a large pit on both sides of a stream culvert that crosses the roadway, and the boring of a new gas main under the culvert.  Due to the nature of this operation, a total road closure (24 hours a day, 7 days a week) will be in place for the duration of the work, which is anticipated to take approximately two weeks.  Traffic on Valley Road will be detoured during construction. View Traffic Detour Plan  During this period, trash/recycling collection, mail/package delivery, school bus service, and residents' access to their homes will be kept available by the contractor.  Questions regarding the project can be directed to:

Joseph Welte - Henkels & McCoy Project Manager - 215-377-1959

Aqua Water Main Replacement Work beginning November 2
In order to improve service reliability for customers, Aqua Pennsylvania will begin the replacement of aging 6-inch cast iron pipe with new 8-inch ductile iron water main on November 2, 2020 at the locations shown below (NOTE: Aqua previously scheduled this work to begin on October 15, 2020).

  • Arbor Road from Ashbourne Road to Pitt Road
  • Boyer Road from Ashbourne Road to Gilbert Road
  • Gilbert Road from Ashmead Road to Croyden Road
  • Rowland Avenue from Ashmead Road to Croyden Road
  • Pitt Road from Arbor Road to Croyden Road
  • Croydon Road from Pitt Road to #201 Croyden Road

Construction will generally take place weekdays between 8 a.m. and 4 p.m.  Access will be provided for emergency, mail and trash service.  Residents will have access to their properties, but at times will need to enter from different directions due to changing work zones.  Aqua will notify customers ahead of any planned water service interruptions.

For any questions regarding the project, contact: Mike Staerk, Aqua Superintendent of Construction, 215-659-2505, ext. 56005

October 19, 2020
Aqua (Wastewater) Pipe Lining work scheduled for October 26-27 on Spring St. and Widener Rd
Aqua (Wastewater) will be lining two short sections of existing sewer pipe located on Spring Street (from Cedar Lane to Old York Road) and on Widener Road (from Whitewood Road to Chelten Hills Drive).  This work is scheduled for October 26th and October 27th, weather permitting, between 7:30 AM and 5:00 PM.  The impact to roadway traffic should be minimal.  Questions can be directed to Hank Wacker, Project Superintendent, at 267-688-1833.

October 6, 2020
Paving Work scheduled for the intersection of Old York Rd and Church Rd beginning October 12
Contractor Allan Myers, LP will be completing punchlist paving work on the Elkins Park Streetscape at the intersection of Old York Road and Church Road from Monday, October 12 through Friday, October 16 from 9:00-3:00 daily.  Lane closures will be in effect. Questions can be directed to Ryan Federsel at (610) 960-3082.

October 5, 2020
PECO Natural Gas Jack and Bore Work on Bickley Road beginning October 14
On October 14, 2020, Henkels & McCoy, a PECO contractor, will begin a jack and bore operation on Bickley Road, between Waverly Road and Toxony Avenue.  This effort involves the excavation of a large pit on both sides of a stream culvert that crosses the roadway, and the boring of a new gas main under the culvert.  Due to the nature of this operation, a total road closure (24 hours a day, 7 days a week) will be in place for the duration of the work, which is anticipated to take approximately two weeks.  Traffic on Bickley Road will be detoured during construction (View Traffic Detour Plan).  During this period, trash/recycling collection, mail/package delivery, school bus service, and resident’s access to their homes, will be kept available by the contractor.  Questions regarding the project can be directed to:

Joseph Welte - Henkels & McCoy Project Manager - 215-377-1959

October 2, 2020
PECO Natural Gas Equipment Replacement Work on Front Street beginning October 5

On October 5, 2020, PECO will begin replacing existing natural gas equipment in the area of Front Street, from Andrea Street to Arbor Road.  This project includes the installation of new underground pipe which is more durable, enhances safety and improves service reliability.  The work will be performed by Henkels & McCoy, a PECO contractor, weekdays between 7:30 a.m. and 4:00 p.m., and will occur in roadways as well as on sidewalks and potentially on private property.  PECO anticipates the natural gas main and service line installation portion of this project will be completed in 4 weeks.  Questions regarding scheduling or the project can be directed to Christopher Long of Henkels & McCoy at (215) 907-0847.

September 28, 2020
Aqua Work on Interceptor beginning B September 28

On Monday, September 28, 2020, Aqua will be starting a project on Interceptor B, beginning in the area of Wall Park and working up towards Cedarbrook Mall.  The work will be done during normal working hours, and there will be no disruption of service.  Aqua’s contractor, Video Pipe Services, will be TVing the interceptor, and in some locations cleaning may be needed.  At this time, no streets will be closed.  The streets where work will occur are:

  • Ivy Lane
  • Rock Lane
  • Lower end of Curtis Park
  • Rock Creek Drive
  • Behind the Wyngate Homes

If you have any questions, please contact Hank Wacker at 267-518-6011 or [email protected]

September 17, 2020

PECO Natural Gas Jack and Bore Work on New Second Street beginning September 22
PECO has an existing detour in place on New Second Street (a state road) between Sunnybrook Avenue and Coventry Avenue, weekdays between 9:00 AM and 3:00 PM, to replace existing natural gas pipelines.  This work is being performed by Henkels & McCoy, a PECO contractor, and is expected to last approximately sixteen more weeks.  On September 22, 2020 Henkels & McCoy will begin a jack and bore operation within the detour work area.  This effort involves the excavation of a large pit on both sides of a stream culvert that crosses the roadway, and the boring of a new gas main under the culvert.  Due to the nature of this operation, PennDOT has approved a total road closure (24 hours a day, 7 days a week) for the duration of this work, which is anticipated to take approximately three weeks.  During this period, trash/recycling collection, mail/package delivery, school bus service, and resident’s access to their homes, will be kept available by the contractor.  Questions regarding scheduling or the project can be directed to:

Joseph Welte - Henkels & McCoy Project Manager - 215-377-1959

Ernie Scull - Henkels & McCoy Site Supervisor - 215-768-8213


September 8, 2020

Limekiln Pike Bridge over SEPTA

This state bridge is located near the intersection of Limekiln Pike and Mt. Carmel Avenue.  The bridge superstructure will be replaced in two phases in order to remain open to pedestrian and vehicle traffic.  Temporary utility relocation work has been underway for some weeks, but PennDOT anticipates implementing Phase 1 work on or about 9/15/20.  This  means that the east side of the bridge will be closed and there will be two lanes of traffic on the west side (one lane in each direction).   The total bridge project is expected to last 15 months.

September 4, 2020
Aqua Water Main Replacement Work beginning Sept 7

In order to improve service reliability for customers, Aqua Pennsylvania will begin the replacement of aging 6-inch cast iron pipe with new 8-inch ductile iron water main on September 7, 2020 at the following locations:

  • Laurel Avenue from Township line Road to #433 Laurel Avenue
  • Beecher Avenue from Laurel Avenue to Elm Avenue
  • Franklin Avenue from Laurel Avenue to Grove Avenue
  • Central Avenue from Ashbourne Road to Highland Road
  • Highland Road from Central Avenue to Rowland Avenue

Construction will generally take place weekdays between 8 a.m. and 4 p.m.  Access will be provided for emergency, mail and trash service.  Residents will have access to their properties, but at times will need to enter from different directions due to changing work zones.  Aqua will notify customers ahead of any planned water service interruptions.

For any questions regarding the project, contact:

Mike Staerk, Aqua Superintendent of Construction

215-659-2505, ext. 56005


July 28, 2020

PECO Natural Gas Equipment Replacement Work on New Second Street beginning August 3
On August 3, 2020, PECO will begin replacing existing natural gas equipment in the area of New Second Street from Cheltenham Avenue to Coventry Avenue.  This project includes the installation of new underground pipe which is more durable, enhances safety and improves service reliability.

The work will be performed by Henkels & McCoy, a PECO contractor, weekdays between 9:00 a.m. and 3:00 p.m., and will occur in roadways as well as on sidewalks and potentially on private property.  Traffic on New Second Street will be detoured during construction.  Natural gas services may need to be shut off while new service is installed to private properties.  Shut offs may last between four and eight hours.  PECO will contact homeowners directly to make service connection arrangements.
View Traffic Detour Plan

Work is expect to last approximately twenty-three weeks. Questions regarding scheduling or the project can be directed to Christopher Long of Henkels & McCoy at (215) 907-0847. Other questions can be directed to PECO at (610) 832-6420 or [email protected].

July 27, 2020
Aqua Plans Night Work to Televise Sanitary Sewer Interceptor A Starting July 27
On July 27, 2020, Aqua plans to begin work televising a 7,500 linear foot section of its Sanitary Sewer Interceptor A, which was postponed from its original scheduled start date of July 12.  This pipeline runs through a golf course and park land, so roadway traffic or residents should not be affected.  The work must be performed at night (11 p.m. to 7 a.m.) when the flow in the sewer lines is at its lowest.  The project is anticipated to take 14 days and go through August 10.
Map of Work Area
Letter from Aqua Describing Work Scope


Aqua Continuing Work to Replace Water Mains on Old York Road

Aqua PA will continue the replacement of aging 6-inch cast iron water mains on Old York Road, from Washington Lane (Abington) to Old York Road Spur (Cheltenham), with 8 and 12-inch ductile iron pipe. Construction will typically take place week days from 9 a.m. to 3 p.m., and is expected to be completed by early November 2020. Lane closures and flagmen will be utilized to maintain traffic through the work zones.

July 17, 2020
PECO Natural Gas Equipment Replacement Work beginning July 21
Beginning on July 21, 2020, PECO contractor Henkels & McCoy will be replacing existing natural gas equipment at the following locations:

  • Bickley Road from E Waverly Road to Church Road
  • Toxony Avenue from Bickley Road to S Easton Road
  • Royal Avenue from Bickley Road to S Easton Road
  • Forsythe Avenue from Bickley Road to S Easton Road

 This work is being performed by PECO in order to enhance safety and improve service reliability.  Work hours will be Monday through Friday, 7:30 AM to 3:00 PM.  PECO anticipates the natural gas main and service line installation portion of this project will be completed within twenty-two weeks.

July 16, 2020
PECO Natural Gas Main Replacement Work on Royal Ave and Gribbel Road beginning Friday, July 17

As part of the PECO Energy gas main replacement project, Kehoe Construction, Inc. will be performing trench restoration and final roadway milling/paving in the area of the Royal Avenue and Gribbel Road intersection, between Friday, July 17th and Tuesday, July 21st (weather permitting).  Work will take place on weekdays between 7:30 AM and 4:00 PM.  Roadways may be closed to thru traffic during construction.  Access will be provided for emergency vehicles, deliveries and trash services.  Residents will have access to their properties, but at times may need to enter from a different direction due to changing work zones.  Kehoe staff members will be available to provide assistance.

July 14, 2020
PECO Natural Gas Equipment Replacement Work on Hillcrest Road beginning July 15
As part of the PECO Energy gas main replacement project, Kehoe Construction, Inc. will be performing trench restoration and final roadway milling/paving on Hillcrest Road, from Cobden Road to Conwell Road, between Wednesday, July 15th and Monday, July 20th (weather permitting).  Work will take place between 7:30 AM and 4:00 PM.  Hillcrest Road will be closed to thru traffic during construction.  Access will be provided for emergency vehicles, deliveries, and trash services.  Residents will have access to their properties, but at times may need to enter from a different direction due to changing work zones.  Kehoe staff members will be available to provide assistance.

July 10, 2020
Aqua Plans Night Work to Televise Sanitary Sewer Interceptor A
On July 12, 2020 Aqua plans to begin televising a 7,500 linear foot section of its Sanitary Sewer Interceptor A.  This pipeline runs through a golf course and park land, so roadway traffic or residents should not be affected.  The work must be performed at night (11 p.m. to 7 a.m.) when the flow in the sewer lines is at its lowest.  The project is anticipated to take 14 days and go through July 27.
Map of Work Area
Letter from Aqua Describing Work Scope

June 24, 2020
PECO Natural Gas Equipment Replacement Work near Waters Road beginning June 29
On June 29, 2020, PECO will begin work to replace
existing natural gas equipment. Work includes the installation of new underground pipe which is more durable, enhances safety and improves service reliability.

Work will take place in the area of Waters Road from Boncouer Road to Hilldale Road between 7:30 a.m. and 3:00 p.m. and will occur in roadways as well as on sidewalks and potentially on private property. Natural gas services may need to be shut off while new service is installed to private properties. Shut offs may last between four and eight hours.

The work will be performed by Henkels & McCoy, a PECO contractor and they will not need access to the natural gas appliances or equipment inside homes.

Work is expect to last approximately eight weeks. Questions regarding scheduling or the project can be directed to Christopher Long of Henkels & McCoy at (215) 907-0847. Other questions can be directed to PECO at (610) 832-6420 or [email protected].

June 22, 2020
Aqua Roadway Restoration Work beginning June 23
On June 23, 2020 Aqua contractor, Caddick Utilities LLC, will begin the roadway restoration work for water main installations at the following locations:

  • New Second Street from Sunnybrook Ave to Lanfair Rd
  • Lanfair Rd from New Second Street to Front St
  • Dewey Rd from Front St to Lanfair Rd
  • Overhill Rd from Sunnybrook Ave to Lanfair Rd
  • Sunnybrook Rd from New Second St to Overhill Rd
  • Brookfield Rd from Sunnybrook Ave to Parkview Rd
  • Elizabeth Rd from Brookfield Rd to Lanfair Rd
  • Normandy Ln from Lanfair Rd to Elizabeth Rd
  • Front St from Parkview Rd to Dewey Rd

Work hours will be Monday through Friday, 7:30 a.m. to 4:30 p.m., except New Second Street hours of work will be 9:00 a.m. to 3:00 p.m., and during those hours New Second Street will be closed with a detour in effect. The entire project is anticipated to take approximately four weeks to complete, weather permitting.

June 19, 2020
Aqua Roadway Restoration Work beginning June 22

Beginning on June 22, 2020, Aqua contractor Apcon, Inc. will be performing final roadway restoration on the following streets:


- Humphrey Merry Way from John Russell Circle to Penrose Ave

- Sycamore Ave from Juniper Ave to Juniper Ave

- Whitewood Rd from Spring Ave to Webb Rd

- Hidden Ln from Spring Ave to #7913 Hidden Ln

Work hours will be Monday through Friday, 7:30 AM to 5:00 PM.  Apcon anticipates this project will be completed by June 26, 2020 weather permitting.

PECO Natural Gas Equipment Replacement Work beginning June 22
Beginning on June 22, 2020, PECO contractor Henkels & McCoy will be replacing existing natural gas equipment at the following locations:

  • Garden Road, from Johns Road to Edgemoor Road
  • Lawnside Road, from Garden Road to Rowland Avenue
  • Rowland Avenue, from N/O Lawnside Road to Johns Road

This work is being performed by PECO in order to enhance safety and improve service reliability.  Work hours will be Monday through Friday, 7:30 AM to 3:00 PM.  PECO anticipates the natural gas main and service line installation portion of this project will be completed within eight weeks.

May 27, 2020
PECO Natural Gas Equipment Replacement Work for June through mid-August

PECO will be replacing existing natural gas equipment in order to enhance safety and improve service reliability as described below. 

Gas main installation work has begun at the following locations and is expected to continue until the end of June:

  • Brookfield Road from Parkview Road to Andrea Road
  • Ivinetta Road from Johns Road to Parkview Road
  • Parkview Road from Ivinetta Road to Rowland Avenue
  • Rowland Avenue from Parkview Road to Lawnside Road

Gas main installation work is scheduled to begin at the following locations on or about June 1, 2020, and is expected to continue through mid-August:

  • 4th Avenue from Asbury Avenue to N/O High Avenue
  • Asbury Avenue from Coventry Ave to Oak Lane Road
  • High Avenue from 4th Avenue to New Second Street   
  • Oak Lane Road from Asbury Avenue to New Second Street   
  • Richards Avenue from Asbury Avenue to Cul-de-Sac
  • Sunnybrook Avenue from 4th Ave to Oak Lane Road

April 30:

PECO Starts Natural Gas Meter and Underground Piping on May 1, 2020
PECO will be performing inspections of natural gas meters and underground piping to ensure the safety of its customers and employees. Beginning May 1st the  Heath Consultants Inc., a qualified PECO contractor will be in Cheltenham to complete inspections of natural gas facilities. Crews and contractors are following all safety protocols, including wearing additional protective equipment and practicing social distancing. All contractors will have a PECO contractor ID badge. There is no cost for the inspection and it will only take a few minutes to complete. Customers will not experience any interruption to their natural gas service and no indoor work will be performed.
Customer Letter

April 13:

Aqua Utility Construction Starts April 20th and New Second Street will be Closed Weekdays for 20 Weeks
Aqua Pennsylvania begins  utility construction Monday, April 20, through Tuesday, June 30, 2020 on weekdays from 9:00 a.m. to 3:00 p.m. closing  New Second Street  between Oak Lane and Cheltenham Avenue in Cheltenham Township. During the closure, motorists will be directed to use Oak Lane and Cheltenham Avenue. Motorists are advised to allow extra time when traveling through the work areas because backups and delays will occur. All scheduled activities are weather dependent.

April 3, 2020
PECO  Upgrading Service Outside of Neighborhoods Starting Monday, April 6, 2020
Henkels & McCoy, a qualified PECO contractor completed the natural gas main installation and will begin upgrading services outside homes on the streets listed below starting April 6th, and the work will be completed.  No access to appliances or equipment inside homes is required.  Only necessary outside work will be completed to begin upgrading your service line. Any areas impacted on your property will be repaired, the streets will be repaved, and all areas will be restored to their original condition.

  • New Street from Wesley Avenue to north of Wesley Avenue
  • Parkside Lane from S. Keswick Avenue to the Cul-de-Sac
  • S. Keswick Avenue from E. Glenside Avenue to Paxson Avenue
  • S. Keswick Avenue from Glenside Avenue to north of E. Waverly Road
  • Wesley Avenue from  S. Keswick Ave to New Street
  • Asbury Avenue from Oak Lane Road to Cheltenham Avenue
  • Oak Lane Road from Cheltenham Avenue to Asbury Avenue
  • Valley Road from Chestnut Avenue to Oak Lane Road

Read Customer Letter

January 28, 2020

AQUA PA Replacing  Water Mains in Cheltenham with a Closure of New Second Street Starts Feb. 3
Aqua will replace an aging 6 inch cast iron water main as part of an infrastructure improvement project in Montgomery County. Work starts Monday, February 3, 2020 on weekdays, and most construction will take place between 7:30 a.m. and 3:00 p.m. on the following streets in Cheltenham, but New Second Street hours of work will be 9:00 a.m. to 3:00 p.m., and during those hours New Second Street will be closed with a detour in effect.

  • New Second Street from Sunnybrook Ave. to Lanfair Rd.
  • Lanfair Road from New Second Street to Front Street
  • Dewey Rd. from Front St. to Lanfair Rd.
  • Overhill Rd. from Sunnybrook Ave. to Lanfair Rd.
  • Sunnybrook Ave. to New Second St. to Overhill Rd.
  • Brookfield Rd. from Sunnybrook Ave. to Parkview  Rd.
  • Elizabeth Rd. from Brookfield to Lanfair Rd.
  • Normandy Lane from Lanfair Rd. to Elizabeth Rd.
  • Front Street from Parkview Rd. to Dewey Rd.

Map PDF from Aqua for New Second Street Detour

The new main will increase service reliability, reduce the potential for main breaks and discolored water and improve water flow in the area. The $1.6952,000 project of 8,443' feet of 8 inch ductile iron pipe with the completion expected by the end of May. 

Following the installation of the new water main, there will be a period of time during which the main will be chlorinated and tested before being put into service. During this phase, activity on the job site will be limited. Once testing has been completed, Aqua will transfer each water service and any fire hydrants onto the new main. It is important to note that the trench will be covered with temporary black top at the end of each work day. Once all of the activity described has been completed, permanent restoration will follow in about 30 to 60 days.

Construction will typically take place daily between 7 a.m. and 3 p.m. Construction on W. Valley Forge will take place between 9 a.m. and 3 p.m. Access will be provided for emergency, mail and trash services. Residents will have access to their properties but at times will need to enter from a different direction due to changing work zones. Aqua will notify customers 24 hours in advance of any scheduled shutdown, however, as with any construction project, an emergency shutdown might be necessary. If so, Aqua will restore service as soon as possible.

Should you have an emergency, including a water quality issue, please call Aqua’s Customer Service Department or emergency dispatcher at  (877.987.2782).





June 19, 2020

Aqua Roadway Restoration Work beginning June 22

Beginning on June



June 19, 2020

Aqua Roadway Restoration Work beginning June 22

Beginning on June
 
 
Cheltenham Township   ~   8230 Old York Road   ~   Elkins Park, PA 19027
Hours: Monday-Friday, 8AM-4:30PM
Phone: 215-887-1000   ~   Fax: 215-887-1561
Site Map   |   Contact Us   |   Disclaimer   |   Powered by MunicipalCMS
Sign up for enews Facebook Get our RSS feeds   
0